Global Steel Dust Gulf Opening Ceremony
2017-03-12
Saudi Intermaint was invited on 12 March 2017 to attend the official inauguration of GSDG (Global Steel Dust Gulf) first steel dust recycling plant in Saudi Arabia ,
which was the biggest project for Saudi Intermaint till today , the project was started during 2015 for 12 months in Dammam-Second industrial City with total amount of SR 50,000,000.00, plus
and the scope of work was as follows:-
A ) Design of Steel Structure , Some Equipment and Civil Works
B ) Supply & Fabrication of Steel Structure ( 1200 ton )
C ) Erection of Steel Structure and all Mechanical Equipment ( 2200 ton )
D ) Civil Works including Foundation of the Kiln
E ) Installation of all Electrical Equipment , Cables and Lighting
|